Chemical Recycling Company Watchlist Scan — 2026-11-09
AI-writtenThis report was written by a scheduled AI sweep of public sources. It may contain errors; check the sources it links before relying on it.
Window: changes since the last watchlist run on 2026-11-02. This was a quiet week: three deltas, all company statements reported in trade press. No new permit or agency action turned up for any watchlist company. Items already logged by the 11-05 and 11-08 sweeps are not repeated: the Waste Energy 11-17 investor call, the PureCycle Q3 8-K, and the Eastman DOE award.
Deltas
PureCycle: overseas spending paused, WM feedstock contract (no site file)
- Source: Resource Recycling, 2026-11-05, reporting the 11-04 Q3 call. These are company statements reported in news, not agency records.
- Discretionary spending on the planned Rayong (Thailand, $250M) and Antwerp plants is paused so the company can focus on Ironton, OH. The CFO calls it “a deliberate capital decision, not a change in our plan.” Rayong received a construction permit in September and stays the next priority once financing closes.
- PureCycle has a three-year WM contract for up to 25 million lb/yr of post-consumer PP bales, starting this month. Fernando Musa, former CEO of Braskem, is now executive chairman.
- Ironton: programs that are shipping or close to it total 45–55 million lb/yr at full ramp. That is about 40–50% of the plant’s 107 million lb/yr nameplate capacity. The article does not mention Augusta, GA.
- Facility match: registry rows
purecycle-ironton-ohandpurecycle-augusta-gaexist but have no facility file. As on 11-08, this run logs the item without a facility slug because the news is corporate. A human may want to open an Ironton file.
LyondellBasell: MoReTec-2 now expected in Europe (lyondellbasell-houston-tx)
- Source: Resource Recycling, 2026-11-02, on the 10-30 call. These are company statements reported in news.
- The article reports that LyondellBasell now expects to build MoReTec-2 in Europe, and only after MoReTec-1 (Wesseling, Germany) starts up. US development would depend on demand and regulation. The idled Houston refinery site, which had been considered for MoReTec-2, is being sold (Valero, logged 11-01).
- Stage stays
delayed. The company has not said Houston will not be built, so thecancelleddefinition is not met. If a formal cancellation comes, the stage moves tocancelled.
Reju: up to 8–10 US plants contemplated (reju-rochester-ny)
- Source: Recycling Today, 2026-11-06, an interview with CEO Patrik Frisk. These are company statements reported in news.
- Reju has looked at about 30 US sites and plans up to 20 plants in the next decade, “eight to 10 of which could be in the U.S.” Rochester is its first US site, and Goodwill of the Finger Lakes is a partner there. There is no Rochester permit, final investment decision or timeline change; the stage stays
proposed. - This is an early warning: more US textile-depolymerization sites are being scouted, and none are named yet.
Checked, nothing new since 11-02
Brightmark, Alterra (no second US site named), Resynergi (relocation site still undisclosed), Encina, ExxonMobil Baytown (no fourth-unit record; the company page on the third unit is dated 2026-02-02 and was already referenced), Eastman Kingsport and Longview, Clean Vision / Clean-Seas Belle (no appeal or monitoring agreement reported), Freepoint, Cyclyx / Agilyx (no Q3 release found), Nexus Circular, Waste Energy (call on 11-17), Loop, Honeywell UpCycle, Syre / Selenis.
Fact-source replacements
None.
Upcoming
- 2026-11-17: Waste Energy Q3 investor call (Midland WE #1 commissioning, targeted 12-01).
- Agilyx Q3 / interim update expected in November (Cyclyx status).